Quantcast
Total Float

Share on Google+Share on FacebookShare on LinkedInShare on TwitterShare on DiggShare on Stumble Upon
Custom Search
 
  
 
The first step in determining the basic schedule is to do a forward pass. The forward pass gives you the total duration of your project. You start with the very first activity and plug in a zero for its early start date. Then add the duration to the early start date to get the early  finish  date.  The  early  finish  date  for  an  activity becomes  the  early  start  date  for  the  next  activity. Notice  that  activity  1050  in  figure  2-13  had  two preceding activities (1020 and 1040) and you chose the  larger   of  the  early  finish  dates  (11  vice  10). Remember  to  add  any  lag  between  the  activities (between activity 1070 and the next activity there are 3 days lag time).  Lag  times  are  mandatory  wait times  between  activities.  A  common  example  is concrete cure times. Cure times require you to wait several days to several weeks after placing concrete before you strip the forms. Follow the following two equations  through  the  network  in  figure  2-13: Early Start  + Duration  = Early  Finish Early Finish  + Lag (if any)  = Early Start (next activity) * Look at the network in figure 2-13, the early start and finish dates for an activity depend on the number and duration of the activities that have to be done before  it. The next step in determining the basic schedule is a backward pass. The  backward  pass  determines  your critical path. You start by taking the early finish date for the last activity and making it the late finish for the last  activity.  For  each  activity,  subtracting  the  duration from the late finish date will give you the late start date. The late start date will become the late finish date for the preceding activity. Notice that activity 1040 in figure 2-13 has two follow-on activities and you took the smaller of the late starts (11 vice 12). Follow the equations shown through the network in figure 2-13. For any activity where the early start is the same as the late start and the early finish is the same as the late finish, that activity is critical! Late Finish – Duration = Late Start Late Start – Lag (if any) =  Late   Finish   (preceding activity)* TOTAL FLOAT Total float is the number of days an activity can be delayed without delaying the project completion date. Looking at activity 1020 in figure 2-13 you see that it could finish as early as day 10 or as late as day 12. The 2 days of leeway between day 10 and day 12 in activity 1020 are called total float. To calculate total float you subtract the early finish date from the late Figure 2-13.—Typical network. 2-16



Construction News
   


Privacy Statement - Copyright Information. - Contact Us

comments powered by Disqus

Integrated Publishing, Inc.
9438 US Hwy 19N #311 Port Richey, FL 34668

Phone For Parts Inquiries: (727) 755-3260
Google +