any reinforcing steel is placed. To ensure proper adhesion of the concrete, keep all bond-breaking materials off the reinforcing steel.
Reinforcing bars (rebar) should be assembled into mats and placed into the forms as a unit. This allows for rapid assembly on a jig and reduces walking on the casting surface, which has been treated with the bond-breating agent.
Extra rebars must be used at openings. They should be placed parallel to and about 2 inches from the sides of openings or placed diagonally across the corners of openings.
The bars may be suspended by conventional methods, such as with high chairs or from members laid across the edge forms. However, high chairs should not be used if the bottom of the cast panel is to be a finished surface. Another method is to first place half the thickness of concrete, place the rebar mat, and then complete the pour. However, this method must be done quickly to avoid a cold joint between the top and bottom layers.
When welded wire fabric (WWF) is used, dowels or bars must still be used between the panels and columns. WWF is usually placed in sheets covering the entire area and then clipped along the edges of the openings after erection.
If utilities are going to be flush-mounted or hidden, pipe, conduit, boxes, sleeves, and so forth should be put into the forms at the same time as the reinforcing steel. If the utilities pass from one cast panel to another, the connections must be made after the panels are erected but before the columns are poured. If small openings are to go through the panel, a greased pipe sleeve is the easiest method of placing an opening in the form. For larger openings, such as air-conditioning ducts, forms should be made in the same reamer as doors or windows.
After rebar and utilities have been placed, all other inserts should be placed. These will include lifting and bracing inserts, anchor bolts, welding plates, and so forth. You need to make sure these items are firmly secured so they won't move during concrete placement or finishing.
With few exceptions, pouring cast panels can be done in the same manner as other pours. Since the panels are poured in a horizontal position, a stiffer mix can be used. A minimum of six sacks of cement per cubic yard with a maximum of 6 gallons of water per sack of cement should be used along with well-graded aggregate. As pointed out earlier, though, you will have to reduce the amount of water used per sack of cement to allow for the free water in the sand. Large aggregate, up to 1 1/2 inches in diameter, may be used effectively. The concrete should be worked into place by spading or vibration, and extra care must be taken to prevent honeycomb around outer edges of the panel.
Normal finishing methods should be used, but many finishing styles are available for horizontally cast panels. Some finishing methods include patterned, colored, exposed aggregate, broomed, floated, or steel-troweled. Regardless of the finish used, finishers must be cautioned to do the finishing of all panels in a uniform manner. Spots, defects, uneven brooming, or troweling, and so forth will be highly visible when the panels are erected.
Without marring the surface, curing should be started as soon as possible after finishing. Proper curing is important, so cast panels should be cured just like any other concrete to achieve proper strength. Curing compound, if used, prevents bonding with other concrete or paint.
Tilt-up panels can be set up in many different ways and with various kinds of power equipment. The choice depends upon the size of the job. Besides the equipment, a number of attachments are used.
The most popular power equipment is a crane. But other equipment used includes a winch and an A frame, used either on the ground or mounted on a truck. When a considerable number of panels are ready for tilting at one time, power equipment speeds up the job.
Many types of lifting attachments are used to lift tilt-up panels. Some of these attachments are locally made and are called hairpins; other types are available commercially. Hairpin types are made on the job site from rebar. These are made by making 180° bends in
Continue Reading