and then place it horizontally from the point at which represents normal Seabee production under average it intersected the diagonal line. You can now read the delay factor from the values given on the right-hand side of the chart. Let's look at an example of the process of adjusting man-hour estimates.
Assume that from the work estimate taken from the tables in P-405, you find that 6 man-hours are needed for a given unit of work. To adjust this figure to the conditions evaluated on your job, assume that the average of foreseen conditions you rated is 87 percent. The corresponding delay factor read from the production efficiency graph is 0.80. You find the adjusted man-hour estimate by multiplying this delay factor by the man-hours from the estimating tables (6 MH x 0.8 = 4.8 as the adjusted man-hour estimate).
The activities in the various labor estimating tables are divided into units of measurement commonly associated with each craft and material takeoff quantities. There is only one amount of man-hour effort per unit of work. This number conditions. As used herein, 1 man - day equals 8 man - hours of direct labor.
No two jobs are exactly alike, nor do they have exactly the same conditions. Therefore, you, as the estimator, must exercise some judgment about the project that is being planned. The production efficiency guide chart and graph (table 2-4 and fig. 2-14) are provided to assist you in weighing the many factors that contribute to varying production conditions and the eventual completion of a project. You can then translate what is known about a particular project and produce a more accurate quantity from the average figures given on the labor estimating tables.
Scheduling is the process of determining when an action must be taken and when material, equipment,