training, military training, and organized training conducted within the battalion.
The battalion sends to 2ndNCB/3rdNCB monthly SITREPs that report on the progress of construction tasking. The accuracy of the SITREPs is a reflection of how well the crew leaders have documented labor expended on the projects (timecards) and the quality of the input provided by the crew leaders and the companies. Figure 2-25 is an example of a SITREP feeder with information, calculations, and totals designed to help you create accurate reports.
The weighted percent for each master activity in figure 2-25 is simply the man-days estimated for that master activity divided by the total project man-days estimated. For master activity 60, rough utilities, the
Figure 2-25. - SITREP feeder example.