Figure 9-4. - Emergency/Service Work Authorization, NAVFAC 11014/21.
will fall during the year, the costs collected against the work involved. You should also review for proper job order will not be known until the end of winter.
Do not use a standing job order to authorize a specific task that is service work in nature. For instance, do not write individual standing job orders for replacing window glass, replacing light bulbs, making emergency repairs, or repairing plumbing leaks.
You should review all the standing job orders periodically to determine the requirement of the work authorized and completeness of the specification of the frequency of work performed, reasons for man-hours estimate and work performance variation, and total maintenance force labor requirements.
Priority assignment of jobs is essential in deciding the importance of each job in relation to other requirements. Manpower and funding limitations may not allow the PWD to do all the necessary and desired